McBean Street Bridge closure Sept 30 – Oct 21
submitted by Kendra Hoskin, Office of Councillor Scott Moffatt
The contractor is planning to install concrete girders, placement of concrete deck and other associated works on the east side of the McBean Street Bridge between September 30th and October 21st, 2019. Unfortunately, these works will require the full closure of McBean Street between Royal York Street and Strachan Street. The full closure of McBean Street is scheduled to commence on Monday, September 30th, 2019 at 10 am. The roadway is scheduled to be re-opened to traffic on October 21st, 2019 at 7 am.
PVMS signs will be installed like last time. Pedestrian access will be maintained during the full closure.If there is any change in the schedule, we will keep you posted. We do apologize for the inconvenience this causes. We are nearing the end of construction on the bridge so there is a light at the end of this tunnel!